Solana audit timeline planner
Enter your mainnet launch date and the size of your code. The planner adds up the phases of a Solana audit, from finding a firm to the fix review, and tells you the latest date to contact auditors. Free, no signup, and nothing you enter leaves your browser.
Pick your launch date to see when you need to contact auditors.
A planning range, not a booking. Real calendars depend on the firm.
Get a shortlist of auditors →How long a Solana audit takes, by phase
| Phase | Typical length |
|---|---|
| Find and book an auditor | 1 week to 2 weeks |
| Wait for the start date | 2 weeks to 8 weeks |
| The review itself | 1 to 12 weeks, by code size and complexity |
| Fix the findings | 3 days to 2 weeks |
| Fix review and final report | 3 days to 1.4285714285714286 weeks |
Worked examples
Anchor, fix review included. Total time from first call to final report.
- Token vesting program, 500 lines: about 5 to 15 weeks.
- Staking program, 1,500 lines: about 5 to 15 weeks.
- Lending protocol, 3,000 lines, 2 programs, oracle: about 6 to 17 weeks.
For the full explanation read how long a Solana audit takes, estimate the price with the audit cost calculator, prepare with the audit readiness checklist and send firms the same brief using the audit RFP generator.
Frequently asked questions
When should I book a Solana audit?
Contact auditors at least 15 weeks before mainnet for a standard 1,500-line program, and earlier for large DeFi protocols. The planner works backwards from your launch date and shows the latest date for the comfortable and the fast case.
Why does the plan take longer than the review itself?
The review is only one phase. Finding an auditor takes 1 week to 2 weeks, the wait for a start date 2 weeks to 8 weeks, fixing findings 3 days to 2 weeks and the fix review 3 days to 1.4285714285714286 weeks.
Can I shorten the timeline?
Freeze the code at a tagged commit before the first call, write a short specification, ship tests and contact firms as soon as the scope is stable. A rush start within two weeks usually costs more.
Does the planner replace an auditor quote?
No. It is a planning range built from typical phase lengths and the audit cost calculator method. The real start date depends on each firm calendar.